Kigali

Renovation of Huye Stadium delayed due to Rayon Sports and APR FC Matches

Author: ISHIMWE Walter
On:18/01/2025 10:19
0 0 0 0 0 Loading... 0

The renovation of Huye International Stadium has been postponed for over a month to accommodate matches involving Rayon Sports and APR FC hosted by Amagaju FC and Mukura VS.

On Friday evening, the Rwanda Football Federation (FERWAFA) issued a statement confirming that, following consultations with the Ministry of Sports and the Rwanda Housing Authority, the stadium renovations would now begin after March 10, 2025. 

FERWAFA stated: “We are pleased to inform all Rwandans, especially football fans, that the renovation of Huye International Stadium will soon begin to elevate it to international standards, enhancing the football experience. The renovations will commence after March 10, 2025, to ensure the league schedule remains unaffected.”

Originally, the renovations were scheduled to start on February 1 and conclude by July 31, 2025. However, the timeline has been pushed back due to upcoming Rwanda Premier League fixtures, including Amagaju FC hosting Rayon Sports on February 22 and Mukura VS hosting APR FC on February 23.

Additional matches at Huye include Mukura VS facing Bugesera FC and Amagaju FC also playing against Bugesera FC. After these games, the stadium will be closed for renovations.

This decision was influenced by the significant revenue generated during the last fixtures where Rayon Sports and APR FC drew large crowds at Huye. Hosting these teams again is expected to attract substantial attendance and income.

Meanwhile, the second-round league schedule also highlights the eagerly awaited clash between APR FC and Rayon Sports, slated for May 10, 2025, at Kigali’s Amahoro Stadium.


 



Author


Inyarwanda BACKGROUND